Liaison Group Meeting 26 February 2013
Estimated completion date and official opening of the road is Saturday 20 April 3013
Review of any Issues:
Work outside of the agreed hours – Fulton Hogan to advise on community on Friday about Saturday work
Council to liaise with community re car cleaning
Wellington City Council willing to arrange exterior cleaning of houses affected by construction – Liaison Group to advise
End part of project involving rollers and vibration may affect Glenside Road residents – to notify
Possibility of speed signs on road was raised and will be investigated
Work to be completed to finish the project 26 February 2013 – 20 April 2013
Complete handrail and paths at the western bridge
Small area of kerbing still to prepare
Continuation of footpath and handrail in middle section
Backfilling behind the footpaths and kerbing
Sediment pond at corner of Stebbings/Glenside Roads to be filled in and swale to be added
Rest of services added and sewerage and storm water completed
Sealing of road – to begin in about ten days - involving a bottom layer of base fill to be rolled and then the bitumen on top
Ongoing Work:
Hydro seeding
Landscaping
Work completed during the period 22 January 2013 – 26 February 2013
Cuts in banks tidied and hydro seeding commenced
Water main – need to connect by bridge
Tidying up the Churton Park end of the road to the western bridge: banks, handrail and footpath
Preparation for the kerbing through the middle section
Continuation of the footpath and handrail through to the eastern end
Sediment pond at corner of Stebbings/Glenside Roads to be partially filled in – awaiting approval from Council
Swale for storm water along Reedy’s property (near temporary bridge)
Two metre retaining wall to be built alongside Reedy’s shed
Services (lighting) put in as far as Reedy’s shed
Worked on sewerage and storm water from shed to eastern bridge– four sumps and six to seven man holes
Liaison Group Meeting 22 January 2013
Review of any Issues:
Gate barriers have been left open occasionally
Speeding trucks down Middleton Road before Christmas
Trucks using Glenside Road to take fill out
Work outside of the agreed hours – Fulton Hogan to advise on community on Friday about Saturday work
Work to be completed during the period 22 January 2013 – 26 February 2013
Tidying the cuts in banks
Hydro seeding commencing on banks
Water main - 80% complete
Tidy up the Churton Park end of the road to the western bridge: wall, handrail, paths, banks
Preparation for the curbing through the middle section
Continuation of the footpath and handrail through to the eastern end
Sediment pond at corner of Stebbings/Glenside Roads to be partially filled in – awaiting approval from Council
Swale for storm water along Reedy’s property (near temporary bridge)
Two metre retaining wall to be built alongside Reedy’s shed
Services (lighting) put in as far as Reedy’s shed
Work on storm water from shed to eastern bridge – four sumps and six to seven man holes
Work Completed during the Period 21 November 2012 – 22 January 2013
Sediment pond at the Churton Park end piped and tidied up
Cuts now complete
Bulk of earthworks completed
Silt pond by Reedy’s drive has been filled in, to allow for progress on road